The Government Accountability Office published a report on Friday regarding the Defense Department's major acquisition programs.
Source: Government Accountability Office
Relevance: primary · Type: background
Confidence100%
The report states that three of the Pentagon's ongoing hypersonic weapons programs are at risk of being delayed or delivering systems that have not been fully demonstrated.
Source: Government Accountability Office
Relevance: primary · Type: background
Confidence100%
The programs detailed in the report are the Air Force's Hypersonic Attack Cruise Missile, the Army's Long Range Hypersonic Weapon, and the Navy's Conventional Prompt Strike.
Source: Government Accountability Office
Relevance: supporting · Type: action
Confidence100%
The report urges the Department of Defense to only use rapid acquisition pathways, such as the Middle Tier Acquisition authority, for programs that require already matured technologies.
Source: Government Accountability Office
Relevance: supporting · Type: quote
Confidence100%
The report stated, "More broadly, these findings contribute to growing evidence that programs using the MTA pathway are not delivering fieldable capabilities faster."
Source: Government Accountability Office
Relevance: supporting · Type: quote
Confidence100%
The report stated, "Rather, the use of the MTA pathway has largely been to develop immature technologies that the department has deemed important for acquisition programs with estimated costs equivalent to [a major defense acquisition program]."
Source: Government Accountability Office
Relevance: supporting · Type: background
Confidence100%
The Hypersonic Attack Cruise Missile is being developed by RTX-subsidiary Raytheon.
Relevance: supporting · Type: event
Confidence100%
Raytheon received a $985 million contract in 2022 to develop the Hypersonic Attack Cruise Missile under a Middle Tier Acquisition contract.
Source: Government Accountability Office
Relevance: supporting · Type: background
Confidence100%
The Middle Tier Acquisition contract requires a program to conduct rapid prototyping and immediately initiate fielding within five years.
Source: Government Accountability Office
Relevance: primary · Type: event
Confidence100%
Delays in finalizing the Hypersonic Attack Cruise Missile's design forced the Air Force to reduce the number of flight tests from seven to five.
Source: Government Accountability Office
Relevance: supporting · Type: background
Confidence100%
The Air Force planned to begin the Hypersonic Attack Cruise Missile's flight testing phase in the second quarter of fiscal 2026.
Source: Government Accountability Office
Relevance: supporting · Type: action
Confidence100%
Program officials told the Government Accountability Office that any additional delays during testing are likely to push the weapon past its due date.
Source: Government Accountability Office
Relevance: supporting · Type: quote
Confidence100%
The report stated, "The program has already descoped the rapid prototyping effort from seven to five planned flight tests."
Source: Government Accountability Office
Relevance: supporting · Type: quote
Confidence100%
The report stated, "If a significant flight test failure occurs, it is likely that the program will not be able to complete all five tests within the 5-year rapid prototyping timeframe."
Source: Government Accountability Office
Relevance: supporting · Type: action
Confidence100%
The Air Force has prioritized efforts supporting the Hypersonic Attack Cruise Missile's first flight test.
Source: Government Accountability Office
Relevance: supporting · Type: action
Confidence100%
Program officials told the Government Accountability Office that this prioritization included conducting parts validation testing while simultaneously completing the weapon's design.
Source: Government Accountability Office
Relevance: supporting · Type: action
Confidence100%
Program officials stated that conducting parts validation testing simultaneously with design completion could require the redesign of key parts if they fail validation testing.
Source: Government Accountability Office
Relevance: supporting · Type: background
Confidence100%
Delays would likely disrupt the Air Force's plans to begin Hypersonic Attack Cruise Missile rapid fielding in the first quarter of fiscal 2027.
Source: Government Accountability Office
Relevance: supporting · Type: background
Confidence100%
The Air Force's budget request for fiscal year 2027 includes $404 million to begin purchasing the Hypersonic Attack Cruise Missile.
Relevance: supporting · Type: background
Confidence100%
The Air Force's budget request for fiscal year 2027 includes $806 million to continue testing efforts, capability enhancement, and investment in industrial base capacity for the Hypersonic Attack Cruise Missile.
Relevance: supporting · Type: action
Confidence100%
The Air Force plans to buy more Hypersonic Attack Cruise Missile weapons to bridge a production gap between the program's prototyping and fielding phases.
Source: Government Accountability Office
Relevance: supporting · Type: quote
Confidence100%
The report stated, "These efforts will commence before the rapid prototyping effort has concluded and before the flight test program has demonstrated all aspects of HACM's planned performance."
Source: Government Accountability Office
Relevance: supporting · Type: event
Confidence100%
The Air Force began buying the AGM-183A Air-Launched Rapid Response Weapon from prime contractor Lockheed Martin in fiscal 2026.
Relevance: supporting · Type: background
Confidence100%
Raytheon and Northrop Grumman are developing the Hypersonic Attack Cruise Missile for the U.S. Air Force.
Relevance: primary · Type: event
Confidence100%
Missing, inconsistent, and unclear work standards for missile production have pushed delivery of the Army's second Long Range Hypersonic Weapon battery to at least six months later than originally planned.
Relevance: primary · Type: event
Confidence100%
The Navy's Conventional Prompt Strike program discovered problems during initial production that resulted in the program and contractor having to address quality issues on the missile production line.
Relevance: primary · Type: event
Confidence100%
Production delays caused the Navy to postpone integrating the Conventional Prompt Strike weapon onto its DDG Zumwalt-class destroyers.
Relevance: supporting · Type: background
Confidence100%
The Army and Navy are jointly developing their hypersonic weapons, with each missile variant sharing a common hypersonic glide body system built by Dynetics.
Relevance: supporting · Type: action
Confidence100%
The Army plans to integrate the Long Range Hypersonic Weapon into ground launchers.
Relevance: supporting · Type: background
Confidence100%
The Army has separate Middle Tier Acquisition rapid fielding efforts to field additional Long Range Hypersonic Weapon batteries.
Relevance: supporting · Type: background
Confidence100%
The Navy developed the Conventional Prompt Strike under a Middle Tier Acquisition contract.
Relevance: supporting · Type: background
Confidence100%
The Navy's sea-launched Conventional Prompt Strike iteration will be deployed from Zumwalt-class destroyers and Virginia-class submarines.
Relevance: supporting · Type: background
Confidence100%
Lockheed Martin serves as the prime integrator on both the Army's and Navy's hypersonic weapons programs.
Relevance: primary · Type: action
Confidence100%
The Army and Navy failed to conduct an industrial base assessment before beginning production that would have highlighted issues and likely prevented delays.
Relevance: supporting · Type: quote
Confidence100%
The report stated, "For these interrelated programs, DOD took steps towards improving the rate of missile production."
Relevance: supporting · Type: quote
Confidence100%
The report stated, "According to program officials, both the LRHW and CPS programs are now conducting production quality reviews."
Relevance: supporting · Type: quote
Confidence100%
The report stated, "For example, program officials told us that the Army worked with a third-party consultant to identify production challenges."
Relevance: supporting · Type: quote
Confidence100%
The report stated, "Similarly, program officials told us that the Navy is conducting its own reviews."
Relevance: supporting · Type: event
Confidence100%
Technical issues discovered during the Long Range Hypersonic Weapon's flight testing phase forced the Army to scrub several tests.
Relevance: supporting · Type: event
Confidence100%
Technical issues pushed delivery of the Long Range Hypersonic Weapon to early 2026, which is over two years past its initial goal.
Relevance: supporting · Type: event
Confidence100%
Complications from early flight tests created a production bottleneck that forced both the Army and Navy to pause manufacturing until the missile had successfully flown.
Relevance: supporting · Type: action
Confidence100%
Officials told the Government Accountability Office that one of the contractors continued to experience issues at its facility.
Relevance: supporting · Type: action
Confidence100%
Officials told the Government Accountability Office that both services were working with the company to implement improvements.
Relevance: primary · Type: event
Confidence100%
The Army began fielding the first Long Range Hypersonic Weapon battery at the end of 2025.
Relevance: primary · Type: background
Confidence100%
The Army is now expected to deliver the second Long Range Hypersonic Weapon battery in early 2027.