A $54 million project to transport water from the Walker County Water and Sewerage Authority treatment plant in Chickamauga, Georgia, to the area south of the McLemore resort on Lookout Mountain is nearing completion.
Relevance: supporting · Type: event
Confidence100%
Walker County Water and Sewerage Authority officials addressed McLemore Cove residents at the Cedar Grove Community Center regarding the infrastructure project.
Relevance: supporting · Type: event
Confidence100%
McLemore Cove residents expressed concern that the new water line would reduce local water pressure.
Relevance: supporting · Type: action
Confidence100%
Officials distributed a letter from Jeremiah Roberts, project manager at CTI Engineers, addressing low pressure concerns for the completed Tatum Road to McLemore waterline and pump station.
Relevance: supporting · Type: background
Confidence100%
A new pump station at the base of the mountain will automatically shut off if system pressure drops below operational levels.
Jeremiah Roberts, Project Manager at CTI Engineers
Relevance: primary · Type: quote
Confidence100%
"The design for the Tatum Road to McLemore waterline and pump station has been completed in accordance with Georgia EPD minimum standards and ensures that the minimum required pressure of 20 psi is maintained throughout the distribution system under all flow conditions."
Philip Schofield, Professional Engineer and Vice President at CTI Engineers
Relevance: supporting · Type: action
Confidence100%
Project consultant Philip Schofield stated the infrastructure includes a 4-million gallon clearwell at the WCWSA water treatment plant in Chickamauga.
Relevance: supporting · Type: action
Confidence100%
A 24-inch water line was constructed from the Coke Ovens in Chickamauga to Mountain View Tank.
Relevance: supporting · Type: action
Confidence100%
A 12-inch water line was extended along Tatum Road near the base of the mountain.
Relevance: supporting · Type: background
Confidence100%
A new pumping station is located off Tatum Road.
Relevance: supporting · Type: background
Confidence100%
The water utility sources its primary drinking water from wells and surface water adjacent to the treatment plant on Lee-Clarkson Road in Chickamauga.
Relevance: supporting · Type: action
Confidence100%
Required easements for the line extending up the mountain were obtained from the Beasley family.
Relevance: primary · Type: action
Confidence100%
The new water line terminates at a 1-million gallon storage tank on Highway 157 at the Walker County and Dade County line.
Relevance: supporting · Type: background
Confidence100%
The McLemore resort property includes the Cloudland Hotel.
Relevance: supporting · Type: background
Confidence100%
The majority of the uphill water line is buried underground, with specific sections anchored to rock faces at bluff areas.
Relevance: supporting · Type: action
Confidence100%
The new water tank will be operated by WCWSA to support the Dade County Water and Sewer Authority.
Relevance: supporting · Type: background
Confidence100%
The additional water supply will enable Dade County to maintain service to the McLemore resort and surrounding mountain areas from its existing storage facility.
Relevance: supporting · Type: event
Confidence100%
The Dade County Water and Sewer Authority and WCWSA are currently negotiating water purchase agreements.
Relevance: supporting · Type: background
Confidence100%
The new water infrastructure will extend service to the Head River section, Griff Johnson Road, and Flarity Road.
Relevance: primary · Type: action
Confidence100%
Walker County government allocated $5 million in federal COVID-19 stimulus funds toward the project.
Relevance: supporting · Type: action
Confidence100%
The remaining project funding was secured through federal ARPA grants.
Relevance: supporting · Type: event
Confidence100%
Georgia Power plans to install a new electrical line along the water infrastructure route to supply power to the pump station.
Brandon Whitley, Head of WCWSA
Relevance: supporting · Type: action
Confidence100%
WCWSA director Brandon Whitley stated that ongoing improvements are planned for the broader water distribution system spanning from the state line to the Cove.
McLemore Cove Resident
Relevance: supporting · Type: quote
Confidence100%
"Water projects should go to taxpaying citizens down here, not to rich mountain folk."
McLemore Cove Resident
Relevance: supporting · Type: quote
Confidence100%
"Water pressure is already so low in my neighborhood that there is not enough for everyone to shower in the evenings."
McLemore Cove Resident
Relevance: supporting · Type: quote
Confidence100%
"Construction crews had tore Tatum Road all to hell."
Relevance: supporting · Type: action
Confidence100%
Officials confirmed that road repairs along Tatum Road will be conducted following construction.