The Iowa Transportation Commission approved a $4.2 billion highway construction program for 2027-31 on June 9.
Relevance: primary · Type: background
Confidence100%
The replacement of the Interstate 80 bridge over the Mississippi River is the highest-cost project in the 2027-31 highway plan.
Relevance: supporting · Type: background
Confidence100%
The Interstate 80 bridge over the Mississippi River is officially named the Fred Schwengel Memorial Bridge.
Relevance: supporting · Type: background
Confidence100%
The Illinois Department of Transportation is the lead agency for the Interstate 80 bridge replacement project.
Relevance: supporting · Type: event
Confidence100%
The Interstate 80 bridge project includes rebuilding the I-80/88 interchange.
Relevance: supporting · Type: event
Confidence100%
Iowa is scheduled to contribute $241.2 million for the Interstate 80 bridge replacement between 2028 and 2030.
Relevance: supporting · Type: event
Confidence100%
The replacement bridge over the Mississippi River will be built on the downriver side of the current bridge.
Relevance: primary · Type: event
Confidence100%
The Gordon Drive Viaduct in Sioux City is scheduled for replacement between 2027 and 2030 at a cost of $206 million.
Relevance: supporting · Type: background
Confidence100%
The Gordon Drive Viaduct project is marked as underfunded and eligible for funding from other sources.
Relevance: primary · Type: event
Confidence100%
The conversion of the at-grade intersection of Iowa Highway 27/58 at Greenhill Road in Cedar Falls into a full interchange is scheduled for 2029 at a cost of $54.65 million.
Relevance: supporting · Type: background
Confidence100%
The intersection of Iowa Highway 27/58 at Greenhill Road in Cedar Falls is marked as underfunded.
Relevance: supporting · Type: background
Confidence100%
The U.S. Highway 61 expressway segment from Mediapolis to Iowa 78 includes a new roadbed and interchange.
Relevance: supporting · Type: background
Confidence100%
The U.S. Highway 61 expressway segment between Iowa 78 and Iowa 92 includes a bypass of Wapello.
Relevance: supporting · Type: event
Confidence100%
The U.S. Highway 61 expressway segment between Iowa 78 and Iowa 92 is slated to cost $165.7 million.
Relevance: primary · Type: event
Confidence100%
The ramp from southbound I-35 to eastbound I-235 at the west mixmaster in Des Moines’ western suburbs is being changed from a cloverleaf loop to a flyover ramp.
Relevance: supporting · Type: event
Confidence100%
The I-35 to I-235 ramp project costs $125 million.
Relevance: supporting · Type: event
Confidence100%
Construction lettings for the I-35 to I-235 ramp project are set for July 28.
Relevance: supporting · Type: event
Confidence100%
The lane expansion between University and Douglas avenues on I-35/80 costs $13.3 million.
Relevance: primary · Type: event
Confidence100%
The U.S. 30 Missouri Valley bypass costs $103.7 million and is scheduled for work in 2028 and 2031.
Relevance: supporting · Type: background
Confidence100%
No projects are scheduled for Dickinson County in the 2027-31 highway plan.
Relevance: supporting · Type: background
Confidence100%
No projects are scheduled for Hardin County in the 2027-31 highway plan.
Relevance: primary · Type: event
Confidence100%
Upgrading I-380 to six lanes between the North Liberty and Swisher exits starts in 2030.
Relevance: supporting · Type: event
Confidence100%
$56.2 million has been allocated for the I-380 upgrade between North Liberty and Swisher exits.
Relevance: primary · Type: event
Confidence100%
I-35 will be six-laned between Iowa 210 and U.S. 30 in the next year at a cost of $58.5 million.
Relevance: primary · Type: event
Confidence100%
A project to expand or replace the U.S. 30 interchange with I-35 will start in 2029 at a cost of $65.74 million.
Relevance: primary · Type: event
Confidence100%
The expansion of I-80 between the northeast mixmaster and U.S. 65 is scheduled for completion in 2027 at a cost of $33.25 million.
Relevance: primary · Type: event
Confidence100%
A grade-and-pave project for the northbound lanes of I-35 from the Cumming exit into Polk County is scheduled for 2027 at a cost of $34.1 million.
Relevance: primary · Type: event
Confidence100%
New bridges for I-80 capable of carrying three lanes of traffic in each direction are planned for the exit at U.S. 169 at a cost of $30.4 million in 2028 and 2030.
Relevance: primary · Type: event
Confidence100%
New bridges for I-80 capable of carrying three lanes of traffic in each direction are planned for the exit at U.S. 63 at a cost of $33 million in 2029 and 2031.
Relevance: primary · Type: event
Confidence100%
New bridges for I-80 capable of carrying three lanes of traffic in each direction are planned for the exit at Iowa 21 at a cost of $17.7 million in 2027-28.
Relevance: primary · Type: event
Confidence100%
New bridges for I-80 capable of carrying three lanes of traffic in each direction are planned for the exit at Iowa 149 at a cost of $32 million in 2027 and 2029.
Relevance: primary · Type: event
Confidence100%
The southbound lanes of I-29 between Iowa 175 and the Blencoe exit will be replaced in 2028 at a cost of $25 million.
Relevance: primary · Type: event
Confidence100%
The rest area on I-80 eastbound near Mitchellville will be replaced in 2028-29 at a cost of $17 million.
Relevance: supporting · Type: event
Confidence100%
The rest area replacement on I-80 eastbound near Mitchellville includes an expansion of truck parking.
Relevance: primary · Type: event
Confidence100%
The rest areas on I-29 near Onawa will be replaced, with the northbound side in 2027 and the southbound side in 2029, at a total cost of $10.25 million.
Relevance: primary · Type: event
Confidence100%
The rest area on I-80 westbound near Underwood will be replaced in 2031 at a cost of $6.2 million.
Relevance: primary · Type: event
Confidence100%
The eastbound I-80 truck parking site north of Wilton will be replaced in 2030 at a cost of $7 million.
Relevance: primary · Type: event
Confidence100%
The U.S. 151 Springville exit project is set for 2028 at a cost of $27.3 million.
Relevance: primary · Type: event
Confidence100%
The plan for U.S. 20 on the west side of Dubuque costs $12.5 million and is scheduled for 2028.
Relevance: supporting · Type: event
Confidence100%
The U.S. 20 plan on the west side of Dubuque adds a frontage road to the south side of the highway.
Relevance: supporting · Type: background
Confidence100%
The U.S. 20 plan on the west side of Dubuque retains at-grade stoplights with Old Highway Road, Northwest Arterial, and Crescent Ridge.
Relevance: primary · Type: event
Confidence100%
An interchange for U.S. 30 on the west side of Nevada will be built in 2028-29 at a cost of $32 million.
Relevance: supporting · Type: event
Confidence100%
All remaining at-grade intersections from the east side of Nevada to Ames on U.S. 30 will be closed once the exit for 610th Avenue/18th Street is completed.
Relevance: primary · Type: event
Confidence100%
The intersection of U.S. 30 and 300th Street in De Witt will become a reduced conflict intersection.
Relevance: supporting · Type: background
Confidence100%
The reduced conflict intersection at U.S. 30 and 300th Street in De Witt is part of a $2.9 million Revitalize Iowa’s Sound Economy grant.
Relevance: supporting · Type: background
Confidence100%
The reduced conflict intersection at U.S. 30 and 300th Street in De Witt will be the second such intersection in the state.
Relevance: primary · Type: event
Confidence100%
Offset right-turn lanes will be installed on westbound Iowa 100 at 44th Street in Marion using a $500,000 Traffic Safety Improvement Program award.
Relevance: primary · Type: event
Confidence100%
Left turns will be banned from Munier Road onto eastbound Iowa 100 next year.
Relevance: primary · Type: event
Confidence100%
Two roundabouts will be placed on U.S. 30 on the south side of Boone in 2027 at a cost of $6.7 million.
Relevance: primary · Type: event
Confidence100%
Roundabouts are coming to the U.S. 18/71 intersection on the north side of Spencer in the upcoming year at a cost of $5.7 million.
Relevance: primary · Type: event
Confidence100%
Roundabouts are coming to the U.S. 59/Iowa 2 intersection just south of Shenandoah in the upcoming year at a cost of $2.8 million.
Relevance: primary · Type: event
Confidence100%
Roundabouts are coming to U.S. 69/126th Street west of Elkhart in the upcoming year at a cost of $3.2 million.
Relevance: primary · Type: event
Confidence100%
The project to replace the U.S. 30/59 bridges over the Union Pacific tracks in Denison is scheduled for 2029.
Relevance: supporting · Type: event
Confidence100%
The intersections with U.S. 30 on both ends of the Denison bridge project will be turned into roundabouts.
Relevance: supporting · Type: background
Confidence100%
The three-way intersections at U.S. 30/59 in Denison have not changed since 1962.
Relevance: primary · Type: event
Confidence100%
The bridge on Iowa 175 over the Des Moines River near Dayton is programmed for replacement in 2028 at a cost of $15.5 million.
Relevance: supporting · Type: background
Confidence100%
The bridge on Iowa 175 over the Des Moines River near Dayton was previously scheduled for 2026 at a cost of $8.4 million.
Relevance: primary · Type: event
Confidence100%
A bridge in Lake View on Iowa 175 is set for replacement in 2029 at a cost of $8 million.
Relevance: supporting · Type: background
Confidence100%
The Lake View bridge on Iowa 175 was previously estimated to cost $3.9 million.
Relevance: primary · Type: event
Confidence100%
The state has $6.9 million included for the replacement of the Burlington Street (Iowa 1) bridge over the Iowa River in Iowa City in 2030.
Relevance: supporting · Type: background
Confidence100%
The city of Iowa City expects overall costs for the Burlington Street bridge replacement to be approximately $30 million.
Relevance: primary · Type: event
Confidence100%
The U.S. 34 bridge over the East Nodaway River and Union Pacific Railroad by Corning will be replaced in 2030 at a cost of $21.2 million.
Relevance: primary · Type: event
Confidence100%
Rehabilitation of the Iowa 149/Business U.S. 63 viaduct in Ottumwa is scheduled for 2031 at a cost of $36.9 million.
Relevance: supporting · Type: background
Confidence100%
The rehabilitation of the Iowa 149/Business U.S. 63 viaduct in Ottumwa was previously scheduled for 2029 at a cost of $33.8 million.
Relevance: primary · Type: event
Confidence100%
A paving project north of the Iowa 149/Business U.S. 63 viaduct in Ottumwa, from Second Street past Woodland Avenue, will take place in 2028 at a cost of $7 million.
Relevance: primary · Type: event
Confidence100%
New bridges are planned for Iowa 175 at Decatur, Nebraska, starting no earlier than 2031.
Relevance: primary · Type: event
Confidence100%
New bridges are planned for U.S. 67 (the Centennial Bridge) at Rock Island, starting no earlier than 2031.
Relevance: supporting · Type: event
Confidence100%
$60 million is set aside for the U.S. 67 bridge project at Rock Island in 2031.